我公司承建的廣東省汕頭市澄海潔源生活垃圾焚燒發(fā)電項目三期煙氣凈化工程于2020年06月09日開工建設(shè)。 The FGC project undertaken by Huaxing for Phase III of Chenghai Jieyuan WTE plant in Shantou, Guangdong was commenced on June 9, 2020.
該項目一、二期原有2x225t/d+1x320t/d三條焚燒線,本期新建規(guī)模1x750t/d+1x20MW汽輪機+1x22MW發(fā)電機。煙氣處理采用“旋轉(zhuǎn)霧化半干法脫酸+干法(碳酸氫鈉)脫酸+活性炭吸附+布袋除塵器+飛灰輸送、存儲及穩(wěn)定化工藝”的煙氣凈化工藝,為我司EPC工程。 The phase I & II for the project have three incineration lines of 2x225 t/d and 1x320 t/d. Phase III built 1x750 t/d + 1x20 MW steam turbine + 1x22 MW generator. The FGC adopts the process of "rotary atomization semi-dry deacidification + dry deacidification with sodium bicarbonate + activated carbon adsorption + bag filter + fly ash conveying, storage and stabilization", which is an EPC project of Huaxing.
華星東方在廣東省的業(yè)績涵蓋包括:東莞駿業(yè)、東莞玖龍、汕頭潮南、普寧、惠陽、肇慶、汕頭澄海、高州、中山等多個項目。 The achievements of HXET in Guangdong Province include Dongguan Junye, Dongguan Jiulong, Shantou Chaonan, Puning, Huiyang, Zhaoqing, Shantou Chenghai, Gaozhou, Zhongshan, etc.