The flue gas cleaning (FGC) project undertaken by Huaxing East for Shanghe Waste Incineration Power Plant in Jinan, Shandong passed 72+24 hours trial operation
2022.12.16
The FGC project undertaken by Huaxing for Shanghe WTE plant in Jinan, Shandong passed 72+24 hours trial operation on September 19, 2022.
The total treatment capacity of the plant is 2X500 t/d. In phase I, 1x500 t/d grate and 1x12 MW condensing steam turbine will be built. In Phase II, 1x500 t/d mechanical grate furnace will be added, and 1x12 MW condensing steam turbine generator is planed. The FGC process applied "SNCR in-furnace denitration + semi-dry deacidification (rotary spray) + NaOH injection system (emergency) + dry injection + activated carbon adsorption + bag filter dust removal + fly ash conveying, storage, and stabilization". It is an EPC project of Huaxing.
At present, Huaxing's achievements in Shandong include Zhucheng, Weifang Phase I & II, Weifang Gaomi, Mouping, Tai'an, Gaomi, Zichuan, Linyi Phase II, Xiaojianxi, Huangdao, Linzi Phase I & II, Linyi Lanshan, Yishui Phase II, Wendeng, Laixi, Dezhou, Longkou, Yiyuan, Changle, Shanghe, Yanzhou, Zaozhuang, Zhangqiu Phase II, Laizhou, Yishui Phase I, etc.