The flue gas cleaning (FGC) project undertaken by Huaxing for Shunyi WTE Phase III in Beijing was commenced on May 9, 2021.
The plant will build 1x800 t/d grate furnance and 1x18 mw condensing steam turbine with an annual operation of 8000 hours. FGC applies SNCR with urea denitrification in furnace + spray dry reactor with Ca(OH)2 + activated carbon and dry deacidification agent injection system with Ca(OH)2 + bag filter+GGH+SGH + SCR reactor with urea + fly ash conveying, storage and stabilization process. This is an EPC project of Huaxing.
The achievements of Huaxing East in Beijing include Tongzhou Phase II, Shunyi Phase III, etc.