我公司承建的福建省漳州北部片區(qū)垃圾焚燒發(fā)電項(xiàng)目煙氣凈化工程于2021年10月8日通過72+24小時(shí)試運(yùn)行。
The flue gas cleaning (FGC) project constructed by Huaxing East for waste incineration power plant in northern Zhangzhou, Fujian passed 72+24 hours trial operation on October 8, 2021.
該項(xiàng)目建設(shè)2×500t/d 焚燒爐+1×25MW 凝汽式汽輪發(fā)電機(jī)組。煙氣處理采用旋轉(zhuǎn)噴霧半干法脫酸+消石灰干法噴射+活性炭噴射+布袋除塵器+飛灰輸送+低溫SCR(預(yù)留)工藝,為我司EP工程。
The plant applied 2×500 t/d boilers and 1×25MW condensing turbine. The FGC consists of SDA semi-dry deacidification + lime dry injection + activated carbon injection + bag house filter + fly ash conveying + low temperature SCR (reserved). It’s an EP project of Huaxing East.
該項(xiàng)目為華星東方在漳州市,繼上環(huán)投漳州一期,二期和瀚藍(lán)集團(tuán)漳州南項(xiàng)目后的第四個(gè)投產(chǎn)的煙氣凈化業(yè)績(jī)。同時(shí)也奠定了華星東方在福建省的業(yè)績(jī)領(lǐng)先地位,涵蓋包括:漳州一期,二期,漳州南,晉江,安溪,石獅,建陽,福州,三明,上杭,霞浦等多個(gè)項(xiàng)目。
This project is the 4th operational FGC accomplished by Huaxing East in Zhangzhou, following the Zhangzhou project Phase I & II of Shanghai Environment Investment and Southern Zhangzhou project of Grandblue Group. Hence, Huaxing East has established its leading role in Fujian province in terms of FGC achievements which includ Zhangzhou Phase I & II, Southern Zhangzhou, Jinjiang, Anxi, Shishi, Jianyang, Fuzhou, Sanming, Shanghang, Xiapu, etc.