我公司承建的安徽省蕭縣一般有機廢棄物處置熱電聯(lián)產(chǎn)項目煙氣凈化工程于2021年12月16日開工建設(shè)。
The flue gas cleaning (FGC) project constructed by Huaxing East for combined heat and power (CHP) plant in Xiao County, Anhui started on December 16, 2021. The general organic waste are used as main fuel.
工程整體效果圖
該項目建設(shè)1×100t/h中溫次高壓水冷爐排鍋爐+1×7.5MW背壓式汽輪機。煙氣處理采用旋轉(zhuǎn)噴霧半干法+消石灰干法+活性炭噴射+布袋除塵器+飛灰輸送、儲存及穩(wěn)定化工藝,為我司EPC工程。
The plant constructed 1×100 t/h water cooled grate boiler with medium temperature and sub-high pressure + 1×7.5 MW back-pressure steam turbine. The FGC adopted rotary spray semi-dry method + slaked lime dry method + activated carbon injection + bag house filter + fly ash conveying, storage and stabilization process. It is an EPC project of Huaxing East.
華星東方在安徽省的業(yè)績涵蓋包括:淮北、蕪湖、天長、廬江、渦陽、和縣、蕭縣生物質(zhì)、無為、霍邱、金寨、含山、涂山熱電、蒙城等多個項目。
Huaxing East's achievements in Ahui Province include: Huaibei、Wuhu、Tianchang、Lujiang、Guoyang、Hexian、Xiaoxian、Wuwei、Huoqiu、Jinzhai、Hanshan、Tushan、Mengcheng etc.